Derrick - Part 2
Solex Logistics project team study into all aspect from engineering point to enhance strength of the derrick to prevent collapse while lifting. Propose a suitable floating crane after taking into consideration of the weight and height of the derrick and also the distance need to cover from the cargo to the barge not forgeting the safety expect, precise workflow and restricted shallow water working area. The full lifting operation take place successfully within 10 hours for the 2 unit of derrick from shore to the barge.